SECTION 1

Ground Preparation

This section of the QuickSet system installation guide covers the steps of fixing the sand before laying the DPM (damp proof membrane) layer, and ensuring the sand height is within a ±5 mm tolerance.

The process involves preparing the surface for the DPM installation by sanding it to a smooth and even level, and measuring the sand height to ensure it falls within the specified tolerance range.

1.1 — Overview Of Sanding Before Laying DPM Layer

1.2 — Fixing Sand Solo With Laser Measurer to Within ±5 mm

1.3 — Fixing Sand with Two People With Laser Measurer to Within ±5 mm